President Museveni has Tuesday afternoon commissioned the first phase of the Uganda-China Free Zone of International Industrial Cooperation project in Tororo.
The first phase of this Sukulu Project includes an office living base, mineral dressing plant, phosphate fertilizer plant, unbaked block plant, machine repair centre and a laboratory centre.
At the completion of the three-phase project undertaken by the Dongsong Energy Group, it would have cost $620m and at its peak of production it will create 2,000 jobs.
The second phase, meant to be complete by July 2019, will see the following plants come on board; a steel plant, glass plant, ferroalloy plant, tin smelting plant, shea processing factory, humic acid fertilizer, cement fireboard plant, and a wood factory.
For the third and final phase, envisaged to happen by 2020, a phosphorus chemical plant, iron foundry and medical glove factory, will be completed.