The National Water and Sewerage Corporation has handed over site to the Contractor (Updeal (U) Ltd) yo embark on pipe laying works for the new Kapenguria-Kapchorwa Town watwr pipeline Project.
Speaking at the site hand over, the Water Supply Infrastructure Development Manager Eng. Denis Taremwa shared that the new 4km bulk transmission main will transfer over 3 million litres of water per day to Kapchorwa Town.
He further said that the pipeline laying works are part of the bigger Kapchorwa Water Supply Improvement Project which entails construction of a new Water Treatment Plant at Kapenguria, modifications in the existing Chebutak Water Treatment Plant, installation of booster stations among others.
The NWSC Managing Director, Dr. Eng. Silver Mugisha shared that the Project was designed in-house and will be financed using NWSC’s internally generated resources.
He confirmed that all the pipes for the pipeline project have already been secured and the Project will be completed by end of May 2018.
Dr. Silver shared that the intervention is in line with NWSC’s Strategic Direction and the Government of Uganda’s Vision of 100% safe water coverage by the year 2020.
He further appreciated the support from customers who are paying bills promptly.
“Customers who pay bills promptly are helping us extend services to more people in the country” he shared.